After three months of all †night work sessions, the machines were built to specification and ready for delivery to Cocable. Frank ’ s daring steps into a new field were fully rewarded, he thought. Everyone was ready for a test run, after the first machine was delivered to Cocable. The CAD model was loaded and it was time to hit the “Start” button.
Beep, beep, beep.
“That’s not good, ” said Frank.
He felt embarrassed that the machine failed in front of everyone. He was sure the machine ran fine before it was delivered. He couldn’t allow his first major deal to fail in any way. The machine was checked over for shipping damages. The connections were double †checked. Everything appeared intact. Frank sat down to review the CAD model and discovered the problem. The model was 62 inches long. This was an issue, considering the RP machines were designed for a maximum of 55 inches.
The original Cocable specs for Frank’s RP machines were for a maximum length of 48 inches. Frank optimized his machines for a length of 48 inches, but to be on the safe side, the machines were capable of 55 †inch designs. Sixty – two inches went outside that range. A machine that could make prototypes that long would require completely different processors, actuators, and adhesion processes. This would be a major redesign of the RP machines. This would take time and a lot of money.
Cocable claims that the original specs for a maximum of 48 inches came from GE. GE claims that it never gave Cocable a maximum length. The first design that GE requested from Cocable was 62 inches long and that had been weeks before. Cocable should have double †checked their RP specs. Nobody wants to take the blame for specifying the prototype design sizes and Frank’s first major product is now going nowhere. Everyone is dissatisfied and two things are for sure: (1) The entire project is running late, and (2) it will be way over budget.
You are a Project Management consultant, and have been commissioned to write a report on this case. Write the report to address the following questions.
Questions to be addresses in the report:
1. What lessons can be learnt from this case?
2. Who do you think should pay for the changes?
3. What could have been done to make sure that the project scope was correct? Get Networking homework help for you today