Your company is going to undertake a project to launch a new limited-quantity seasonal product. The activities involved in the project (including activity durations and dependency relationships) are shown in the table below.

Don't use plagiarized sources. Get Your Assignment on
Limited-Quantity Seasonal Product Assignment | Top Essay Writing
Just from $13/Page
Order Now

Top Essay Writing Help

The project launch date is March 2, 2020. Use this information to create a project plan in Microsoft Project (MSP). Be sure to include an MSP-generated work breakdown structure (WBS) column in your project plan.

Use MSP’s Project Summary Task feature to compute the overall project duration. Save your MSP file under the name HW5. Submit your MSP file (.mpp) for grading in the usual way.

Activity

Predecessor

Duration (Weeks)

A. Survey the market

2

B. Design product

3

C. Order raw materials

A

3

D. Receive raw materials

C

2

E. Build a product prototype

D, J

1

F. Develop a marketing plan

E

2

G. Launch full-scale production

E

4

H. Deliver products

F

2

J. Process regulatory approvals

B

3

Please give me the steps on how to do this project on the software. Get Operations Management homework help today