King Ltd enters into a fixed price contract for $18 000 000 to build a train station for Hunter Ltd. It will take 3 years to build the station. The project is expected to be completed by the end of 2020. King Ltd’s estimate of contract costs is $16 000 000 at the commencement of construction. However, the expected costs to complete a construction project can change throughout the project.
The following data relates to the project:
2018 2019 2020 Progress billing to date 4 000 000 12 000 000 18 000 000 Cash collection to date 3 500 000 11 500 000 18 000 000 Costs for the year 4 000 000 8 500 000 4 000 000 Costs incurred to date 4 000 000 12 500 000 16 500 000 Estimated costs to complete 12 000 000 4 000 000 —